Topic 1, Volume A

Question No: 61 – (Topic 1)

You work as a project manager for PassGuide Inc. You do not want to change the task relationship, but you require a quot;waiting timequot; before the starting of the activity can begin. Which of the following is the best approach to alleviate this issue?

  1. Add management reserve to the project activities.

  2. Add lag time to the project activities.

  3. Add lead time to the project activities.

  4. Add float to the project activities.

Answer: B

Question No: 62 – (Topic 1)

You work as a project manager for PassGuide Inc. You want to demonstrate how a process performs over time and when a process is subject to special cause variation, resulting in an out-of-control condition. Which of the following Perform Quality Control tools will help you accomplish the above task?

  1. Control chart

  2. Scatter diagram

  3. Cause-and-effect diagram

  4. Pareto chart

Answer: A

Question No: 63 – (Topic 1)

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

  1. Mitigation

  2. Acceptance

  3. Transference

  4. Avoidance

Answer: C

Question No: 64 – (Topic 1)

You work as a project manager for PassGuide Inc. You are working on the Plan quality process for your project. Which of the following are inputs of the Plan quality process?

Each correct answer represents a complete solution. Choose all that apply.

  1. Scope baseline

  2. Stakeholder register

  3. Project document updates

  4. Cost performance baseline

Answer: A,B,D

Question No: 65 – (Topic 1)

You work as a project manager for PassGuide Inc. You are working on directing and managing the execution of your project. Which of the following is the most likely outcome as part of this phase of the project?

  1. Quality control measurements

  2. Quality metrics

  3. Deliverables

  4. Organizational process assets update

Answer: C

Question No: 66 CORRECT TEXT – (Topic 1)

Fill in the blank with the appropriate term.

The defines the period in which, during the development of the project scope statement, a clear and very thorough project scope statement narrative is documented.

Answer: develop project scope statement period

Question No: 67 – (Topic 1)

Which of the following theories describes the statement below?

quot;It states that there are certain factors in the workplace that cause job satisfaction, while a separate set of factors cause dissatisfaction.quot;

  1. Herzberg#39;s theory

  2. Ouchi#39;s Theory Z

  3. McGregor#39;s X and Y

  4. Expectancy theory

Answer: A

Question No: 68 – (Topic 1)

Dawn is the project manager of the HQQ Project and she believes the project work is done. She has prepared the final project report, which includes information on the financial performance, schedule performance, and project team performance in the project. All of the following documents are used to measure the completeness of the project scope except for which one?

  1. Project scope statement

  2. Project charter

  3. Project WBS Dictionary

  4. Project WBS

Answer: B

Question No: 69 – (Topic 1)

You are a new Project Manager who has been entrusted with a project. You have been directing and managing the execution of your project. Which of the following is the most likely outcome as part of this phase of the project?

  1. Expert Judgment

  2. Lessons learned

  3. Project Charter

  4. Approved Deliverables

Answer: D

Question No: 70 – (Topic 1)

You work as a project manager for PassGuide Inc. You have to address the following information on the business case justifying the project, including return on investment. Which of the following documents will you use to address the above information?

  1. Project charter

  2. Risk register

  3. Stakeholder register

  4. Project scope statement

Answer: A

100% Ensurepass Free Download!
Download Free Demo:GCPM Demo PDF
100% Ensurepass Free Guaranteed!
Download 2017 EnsurePass GCPM Dumps

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.